Public Notice - Construction
Construction is scheduled to begin on Monday, Oct. 26, 2026, with completion expected in December 2027. A full closure of Fort Street from 120th Street to Tranquility Park Road will be in place during the
duration of the project to safely accommodate the work. More Information
Fort Street - 120th to Park Entrance Road
Fort Street between 120th Street to the entrance of Tranquility Park is planned to be reconstructed to a four-lane roadway, divided by a median.
Project Features
Improvements
- Widening of existing lanes
- Addition of storm sewers
- Installation of sidewalks
- ADA-compliant curb ramps
- Multi-use trail
- Bridge replacement
- Street lighting
- Intersection improvements
- Enhanced safety and capacity for all users
Schedule
- Final Design: February 2025 - July 2026
- Right of Way Process: September 2025 - July 2026
- Utility Relocations: September 2025 - October 2026
- Construction: October 2026 - October 2027
Document Library
Design Plans, Studies & Reports
Community Engagement
October 15, 2026 Public Meeting
Contact the Project Team